Helping reduce the impact and frequency of roadworks on city centre traffic through the adoption of innovation and best practice

City London
Country United Kingdom
Year 2020
Markets Access covers and gratings
Company Lumen
Roads works with signs

The issues faced

The disruption caused by street works at peak times on busy city streets often results in lengthy delays to road users and escalating costs for the network owner through the application of permits, lane rental charges, fines and overrun penalties. The failed reinstatement of ironwork is a common problem that adds to the growing costs and delays.

The findings

Traditional methods of installation using industry standard materials and processes would require a typical lane closure of 24 hours. In many cases the road is opened to traffic much sooner meaning the materials have not fully cured. This introduces a weak element to the integrity of the installation which often leads to the premature failure of the reinstatement requiring repeat visits to rectify the problem causing further costs and disruption.

Reduction or lowering of Impact to traffic and road users is regarded as a major win by all UK Highway and Transport Authorities, that coupled with our joint trials at multiple locations across the City of London area, was also regarded as Innovative and Collaborative works to find a suitable solution to reductions in Section 81 Defects.

Field Operations
Lumen
The value

By adopting a collaborative approach to product selection and installation, Lumen has significantly increased the longevity of an installation. This has been acknowledged by the City of London who have awarded Lumen the Highly Commended Gold Award, in recognition of the contribution to reducing whole life costs and helped ensure road users suffer no further inconvenience or disruption.